Step-by-Step Guide for Project Process

TypeStepsStageProcess ByActionRequired FieldsUseful Tools
Project - K&F (BU)1Quote / Tender - Item Cost EstimationProject Sales / ProcurementCreate "Dummy PO" from the dummy project template for estimation


2Tender AwardMichealCreate Project, Copy from Tasks lines from Template


3Billing for DepositFinanceCreate AR Invoice


4Drawing Approved and Purchase Item ConfirmedProject TeamCreate PO from Project Planning Line


5Place order to VendorProcurementPrint out the order and sign by management for approval


6Follow up the Offer/AB no.ProcurementUpdate to PO,
Split AB function

7Shipping Document ReceivedProcurementEnter item tracking line then post ReceiptItem Tracking Line

8Pick Good LogisticPrint the Good Picking document from Transfer Order


9Goods Deliver to WHLogisticPost Transfer Receipt


10Prepare for deliveryProject teamCreate LD
Get Line from Project

11DeliveryProject TeamPrint Delivery Acknowledge


12DeliveredProject TeamPost "Deliver Project Item" in LD


13Update project cardMichealUpdate Project Card 


14Handover to CSTBCMark "End Date" in Project Card


15CS PreparationCSCreate customer for End user (Import)


16CS PreparationCSCreate Services Item according to "Unit") (Import)


17Complete project TBCVerify all billing and payment are settled. 
mark completes







Project - KA (WOLF, SUBZERO)1Quote / Tender - Item Cost EstimationProject TeamCreate Dummy Sales Order for Cost estimation


2Tender AwardedMichealCreate Project, Copy from Tasks lines from Template


3Billing for DepositFinance



4Drawing Approved and Purchase Item ConfirmedProject Team



5Place order to VendorCSFollow-up Vendor Order No


6Split PO Line if delivery date changedCS

*New Customization

7Shipping Document ReceivedProcurement



8Pick Good Logistic



9Goods Deliver to WHLogistic



10Prepare for deliveryProject team



11DeliveryProject Team



12DeliveredProject Team



13Update project cardMicheal



14Handover to CSTBC



15CS PreparationCS



16CS PreparationCS



17Complete project TBC









Import for create Services item