Step-by-Step Guide for Project Process
Type | Steps | Stage | Process By | Action | Required Fields | Useful Tools |
Project - K&F (BU) | 1 | Quote / Tender - Item Cost Estimation | Project Sales / Procurement | Create "Dummy PO" from the dummy project template for estimation | ||
2 | Tender Award | Micheal | Create Project, Copy from Tasks lines from Template | |||
3 | Billing for Deposit | Finance | Create AR Invoice | |||
4 | Drawing Approved and Purchase Item Confirmed | Project Team | Create PO from Project Planning Line | |||
5 | Place order to Vendor | Procurement | Print out the order and sign by management for approval | |||
6 | Follow up the Offer/AB no. | Procurement | Update to PO, | Split AB function | ||
7 | Shipping Document Received | Procurement | Enter item tracking line then post Receipt | Item Tracking Line | ||
8 | Pick Good | Logistic | Print the Good Picking document from Transfer Order | |||
9 | Goods Deliver to WH | Logistic | Post Transfer Receipt | |||
10 | Prepare for delivery | Project team | Create LD | Get Line from Project | ||
11 | Delivery | Project Team | Print Delivery Acknowledge | |||
12 | Delivered | Project Team | Post "Deliver Project Item" in LD | |||
13 | Update project card | Micheal | Update Project Card | |||
14 | Handover to CS | TBC | Mark "End Date" in Project Card | |||
15 | CS Preparation | CS | Create customer for End user (Import) | |||
16 | CS Preparation | CS | Create Services Item according to "Unit") (Import) | |||
17 | Complete project | TBC | Verify all billing and payment are settled. | mark completes | ||
Project - KA (WOLF, SUBZERO) | 1 | Quote / Tender - Item Cost Estimation | Project Team | Create Dummy Sales Order for Cost estimation | ||
2 | Tender Awarded | Micheal | Create Project, Copy from Tasks lines from Template | |||
3 | Billing for Deposit | Finance | ||||
4 | Drawing Approved and Purchase Item Confirmed | Project Team | ||||
5 | Place order to Vendor | CS | Follow-up Vendor Order No | |||
6 | Split PO Line if delivery date changed | CS | *New Customization | |||
7 | Shipping Document Received | Procurement | ||||
8 | Pick Good | Logistic | ||||
9 | Goods Deliver to WH | Logistic | ||||
10 | Prepare for delivery | Project team | ||||
11 | Delivery | Project Team | ||||
12 | Delivered | Project Team | ||||
13 | Update project card | Micheal | ||||
14 | Handover to CS | TBC | ||||
15 | CS Preparation | CS | ||||
16 | CS Preparation | CS | ||||
17 | Complete project | TBC | ||||
Import for create Services item | ||||||