Step 3 - Select Process, Copy Job Tasks from… action
Step 4 - Select Job template record for copy the job tasks line (i.e. Project Tasks)
...
- Click on Start Date field to open the job planning lines card
- To easy to fill up job planning line for all tasks, clear the Job Task No. filer (1) , then click Edit List action (2), and then open the page to new window
- Separate line for start date and end date.
- If the tasks are planned to complete in 1 day, you need to create 2 line for the tasks.
- 1st line enters the plan start date and 2nd line enter the plan complete date.
Step 7 - Close the page after completing the schedule.
Step 8 - Print Project Schedule Excel File from Jobs
...
- Open the excel file, then click Run
- Enter the filter criteria (e.g. Job No, and the project start / end date)
- Save the excel file after the report is retrieved.
For more details, please see Basic Operation - Job (i.e. Project)